Transmission Constraints Leave Thar Plants Underutilised

power-plants

Despite the full-page promotions to check the progressive authorizing of 2,400-megawatt coal power plants in Thar, the state-supported sole power purchaser can’t despatch more than 75% of the total limit. Just 1,800MW of the 2,400MW Thar power plants can be emptied at some random time inferable from transmission requirements. Postpones in the development of the subsequent transmission line among Thar and Matiari Converter Station have brought about the coal-based power plants sitting inactive regardless of positioning exceptionally on the legitimacy request of effective power makers. Focal Power Buying Organization Assurance…