NGC Blames Chinese Contractor for 14–16-Month Delays in Dasu Transmission Line Project

New-Project266

ISLAMABAD: The National Grid Company of Pakistan Limited (NGC) has rejected allegations by Chinese contractor Sinohydro Corporation Limited that delays in the execution of the 765-kilovolt (kV) Dasu Hydropower Project transmission line were caused by the employer and consultant, holding the contractor responsible for slippages of 14 to 16 months in key project activities.

In a strongly worded response dated November 16, 2026, to Sinohydro’s letter of November 2, the NGC Project Management Unit (PMU) said the contractor’s claims regarding pending payments, engineering approvals, right-of-way (ROW) availability, access-road payments and statutory clearances did not accurately reflect the causes of the project’s slow progress.

The correspondence concerns Contract No. WB-DASU-TL-01/2022 for the design, supply, installation, testing and commissioning of a 765kV double-circuit transmission line connecting the Dasu Hydropower Project with Mansehra Grid Station under Lot-I.

Sinohydro had blamed the employer and consultant for delays, citing outstanding payments, returned invoices and progress certificates, access-road costs, engineering and foundation design approvals, ROW availability and pending forest-related no-objection certificates (NOCs).

However, NGC maintained that the contractor had failed to fulfil several of its contractual obligations and had also bypassed the prescribed communication procedure by addressing its letter to the Managing Director instead of the Project Manager.

NGC rejects payment and access-road allegations

Responding to the payment dispute, NGC clarified that payments were governed by Clause 12 of the General Conditions of Contract (GCC) and Appendix 1, which stipulate that payments must be made against work actually performed, measured and duly certified by the employer.

It said Sinohydro could not combine disputed amounts with legitimate payment claims when such amounts had neither been accepted nor agreed upon by the consultant or Project Manager.

NGC, however, assured that all legitimate and duly certified claims were being processed for payment in accordance with contractual provisions.

On access-road payments, the company said its earlier proposal for a payment mechanism was intended to address conflicting positions arising from the contractor’s deviation from the agreed Work Programme.

It emphasised that the original contractual payment arrangements remained unchanged and that Sinohydro was responsible for constructing the access roads required for transmission-line development.

Engineering deficiencies blamed for approval delays

NGC also rejected allegations of delays in engineering approvals, arguing that Sinohydro had repeatedly failed to submit the required optimisation studies, supporting calculations and complete technical information despite several requests.

According to the employer, preparing and submitting technically compliant engineering documents for review was the contractor’s contractual responsibility.

NGC further disclosed that the consultant had gone beyond its normal review obligations by developing engineering solutions for additional leg extensions of special tower types D7M and D7L to facilitate progress.

The designs were shared with Sinohydro through the consultant’s letter dated October 23, 2026, and NGC’s communication of October 30, 2026.

The contractor was subsequently asked to review and validate the designs, complete tower verification and submit outstanding cross-diagonal profiles required for implementation. However, NGC said Sinohydro had yet to provide timely confirmation and the necessary engineering inputs.

The employer has now asked the Chinese contractor to confirm within 14 days whether it accepts the proposed designs as its own under the relevant contractual provisions or submit specific reservations to enable the Project Manager to determine the way forward.

NGC also pointed out that Sinohydro had failed to make its design team available in Pakistan during the consultant’s expert mission from September 9 to 17, 2026, which had specifically been arranged to resolve outstanding engineering issues. The matter was formally communicated to the contractor on September 25.

Dispute over foundation designs

The response also highlighted disagreements over wet-pile and dry-pile foundation designs.

NGC maintained that revisions to wet-pile foundation designs were necessary after the consultant identified technical deficiencies and opportunities for optimisation to ensure safety, constructability, adequacy and cost-effectiveness.

It rejected Sinohydro’s contention that these revisions constituted delays caused by the employer or consultant, describing them instead as part of the contractor’s routine engineering responsibilities.

Regarding dry-pile foundations, NGC said Sinohydro had proposed this solution at approximately 104 locations without adequately demonstrating why conventional foundation designs, hill-cutting measures or other technically feasible alternatives could not be adopted.

The contractor had repeatedly been asked to provide technical justifications and supporting engineering assessments, NGC added.

It maintained that the responsibility for preparing technically sound and complete foundation designs rested with Sinohydro.

NGC disputes contractor’s ROW claims

On the issue of right of way, NGC presented a different account from that provided by the Chinese contractor.

It said at least 20 to 25 work fronts had remained available to Sinohydro at any given time, but most were not utilised, particularly in Section-I, because the contractor had failed to arrange other essential requirements, including subcontractors, tower stubs and approved designs.

NGC further claimed that ROW clearance activities had not even been attempted at more than 100 locations because Sinohydro had failed to mobilise the necessary resources.

Regarding forest and National Highway Authority (NHA) NOCs, the company maintained that obtaining these clearances was primarily the contractor’s risk and responsibility, although NGC was required to facilitate the process.

It accused Sinohydro of portraying these matters as failures by National Grid to divert attention from its own contractual obligations.

NGC identifies major contractual slippages

To substantiate its position, NGC cited several key activities that had suffered delays of 14 to 16 months during the initial two years of the project, despite being largely within the contractor’s control and independent of ROW availability.

These included:

Route survey and revalidation: The activity, including preparation of the plan and profile, was scheduled for completion by June 3, 2023, but was completed in August 2024, approximately 14 months behind schedule.

Tower designs: Designs for D7N and D7H towers, covering a major proportion of the required towers, were due by November 24, 2023, but were finalised only in March 2025, representing a delay of around 14 months.

Pile foundation construction designs: Originally scheduled for October 15, 2023, these designs remained under consideration, with the last approved document dated November 10, 2026.

Prototype tower load testing: The testing, a prerequisite for mass production, was scheduled for December 5, 2023. However, retesting of D7N and D7T towers was completed in April 2025 and May 2026, respectively.

NGC argued that these delays demonstrated persistent failures by Sinohydro to meet its contractual milestones.

It further maintained that ROW possession was to be provided in accordance with the agreed Work Programme and that the contractor could not attribute delays to ROW constraints when its own construction prerequisites had not been fulfilled.

NGC reserves contractual rights

The company also referred to contractual provisions governing claims, arguing that Sinohydro’s November 2 communication did not constitute a formal notice of claim or a fully detailed claim under the relevant contractual clauses.

NGC reserved its right to reject claims that had not been notified within the prescribed contractual timeframe.

It also clarified that its response should not be interpreted as an admission of liability, acceptance of any claim, approval of a change order or waiver of any contractual rights.

The dispute highlights widening differences between NGC and its Chinese contractor over responsibility for delays in the construction of a strategically important transmission line designed to evacuate electricity from the 4,320-megawatt Dasu Hydropower Project.

Story by Mushtaq Ghumman